| Project | Name of Client | Description of Work | Current Status |
|---|---|---|---|
| Dasna Project | GR Infra Projects Limited | Casting, Erection, Transportation of RE Wall Panel. Cost of Project was Rs 132 Lakh. | Completed |
| Migu Project | GR Infra Projects Limited | Casting, Erection, Transportation of RE Wall Panel. Cost of Project is Rs 95 Lakh. | Running |
| Delhi –Vadodara NH-I48N Expressway at Ratlam KAKA Project | GR Infra Projects Limited | Casting, Erection, Transportation of RE Wall Panel. Cost of Project is Rs 140 Lakh. | Running |
| Nashik Project | Dinesh chandra R. Aggarwal Infracon Pvt Ltd | Casting, Erection, Transportation of RE Wall Panel. Cost of Project was Rs 47 Lakh. | Completed |
| UP Project | Dilip Buildcon limited | Casting, Erection, Transportation of RE Wall Panel. Cost of Project was Rs 80 Lakh. | Running |
| NH 754K Amritsar- Jamnagar Economic Corridor | Raj Shyama Constructions Pvt Ltd | Erection of Precast Re Wall works, Transportation of RE Wall Panel. Cost of Project is Rs 120 Lakh. | Running |
| MTN of PMGSY road at Jabalpur MTN 18556 | M.P Rural Road development authority | MTN of PMGSY work. Cost of Project was Rs 18 Lakh. | Completed |
| Dhapewada –Kalmeshwer –Gondkari NH-547 in State of Maharashtra | Dilip Buildcon limited | Casting , Shifting , Erection of RE Wall work. Cost of Project was Rs 75 Lakh. | Completed |
| RS Wall at VUP at bhandhwari Gurgaon – Faridabad Road | Nilofer Engineering | Erection of RE- Wall at Bhandhwari, Gurugram. Cost of Project was Rs 15 Lakh. | Completed |
| Panipat Highway project | Jakson Engineering | Casting, Erection, Transportation of RE Wall Panel. Cost of Project was Rs 56 Lakh. | Completed |
| Premakheda 1 and 2 at Kamod minor canal | Narmada valley development authority, Jabalpur, MP | Construction and cc lining in FY 2016-17 and FY 2017-18. Cost of Project was Rs 59 Lakh. | Completed |
| Khamod 1 and kamod 2 at Kamod minor canal | Narmada valley development authority, Jabalpur, MP | Construction and cc lining in FY 2016-17 and FY 2017-18. Cost of Project was Rs 79 Lakh. | Completed |
| Bharatmala Pariyojana, NH From Raisinghnagar – Pogal (PAU) Project | GR Infraprojects Limited | Erection of Precast Rewall works, Transportation of RE Wall Panel. Cost of Project is Rs 11.09 Lakh. | Completed |